Public Domain
1 New civic space including upgrade to Redfern Street
thoroughfare
Creation of
new civic space and upgrade to Redfern
Street thoroughfare in the Redfern Railway
Station, Gibbons and Regent Streets site. This includes, site preparation,
planting (planting beds, tree pits and trees), irrigation, paving, street
furniture, lighting, and public art. $2,900,000 Medium Term
2 Little Eveleigh park (North
Eveleigh)
Creation of
a new park on the eastern section of North Eveleigh.
Works include site preparation, planting (planting beds, tree pits and trees),
retaining walls, irrigation, paving, street furniture, and lighting. $3,060,000
Medium Term
3 Fan of Tracks park (North
Eveleigh)
Creation of
a new open space on a portion of the Fan of Tracks in North
Eveleigh. Works include site preparation, planting (planting beds,
tree pits and trees), paving, street furniture, play ground, lighting and
public art. $2,850,000 Medium Term
4 Traverser 1 (North
Eveleigh)
Creation of
a new open space on Traverser 1 in North Eveleigh.
Works include site preparation, new planting (planters, feature planting, tree
pits and trees), irrigation, paving, street furniture, and lighting. $3,600,000
Short Term
5 The public garden open space (North Eveleigh)
Creation of
a new open space on the western section of North Eveleigh.
Works include site preparation, planting (tree pits and trees), turf,
irrigation, paving, street furniture, lighting and public art. $2,110,000
Medium Term
6 New open space at the former Rachel Forster
Hospital site
Creation of
a new open space along Pitt Street.
Works include site preparation, planting (planting beds, planting, trees),
paving, street furniture, lighting and public art. $130,000 Short Term
7 Upgrade to Gibbons Street public domain
Upgrade to
footpath, planting (tree pits and trees), lighting and street furniture along Gibbons Street.
$550,000 Short Term
8 Minor public domain works to Wilson Street
Improvements
to planting along Wilson Street
and upgrade footpath where required. $200,000 Short Term
9 Improvements to public domain in Eveleigh Street
site
Improvements
to footpaths, planting, lighting and street furniture. $100,000 Short Term
Total For Public Domain $15,500,000
Road, Public Transport and Access Infrastructure
10 Gibbons
Street
traffic management
Traffic
management on Gibbons Street
to improve pedestrian safety and amenity along street and improve traffic
circulation. $15,000,000 Medium Term
11 Pedestrian and cycle bridge between North
Eveleigh and Australian
Technology Park
Design and
construction of a new pedestrian and cycle bridge between North
Eveleigh and ATP. $2,500,000 Short Term
12 New service road parallel with Wilson Street, North
Eveleigh
Construction
of new service road in North Eveleigh parallel
to Wilson Street.
$1,600,000 Short Term
13 Upgrade of intersection at North
Eveleigh with Wilson
Street (Iverys
Lane end)
Upgrade
works to intersection. $65,000 Short Term
14 New intersection at Wilson
and Shepherd Streets to new service road in North Eveleigh
New
intersection works. $80,000 Short Term
15 Local intersection upgrades at Cleveland
& Shepherd Streets Intersection upgrade.
$40,000
Short Term
16 Upgrade of Boundary Street between Regent and
Gibbons Streets
Upgrade of Boundary Street.
$60,000 Medium Term
17 Full directional sign program for
pedestrians, cyclists & motorists
Installation
of signage. $55,000 Short Term
18 General contribution to improvements to
bicycle paths Improvement to street markings and signage
$500,000
Medium Term
Total for Road, Public Transport and Access Infrastructure $19,900,000
Community Facilities
19 New childcare facility New childcare facility
to service the new residents and workers.
Multi purpose
centre. $1,200,000 Medium Term
Total for Community Facilities $1,200,000
Drainage
20 Local flooding and drainage works Stage 1 –
Investigations and feasibility $100,000 Short Term
Stage 2 –
Design Subject to outcome of Stage 1 Medium Term
Stage 3 –
Construction Subject to outcome of Stage 1 and 2 Medium Term
Total for Drainage $100,000 Plus a further
cost subject to outcome of Stage 1 and 2.