RULES OF CONSTRUCTION
- A
community liaison group must be prepared who have details of the works,
the community communication plan, complaints management plan and are
provided all reasonable requests for information - Prior
to any work commencing, the community must be notified and given full
details. - Construction
hours are Mon to Fri, 7am to 6pm and Sat 8am to 1pm except for emergency
or safety requirement - Operational
noise should be within work hours and comply with the NSW Noise Policy - All
heavy vehicles should enter via the temporary road. A secondary access
route via City Road,
Golden Grove, Wilson,
Burren St can be used in exceptional circumstances (largely in initial
construction). - Complaints
should be responded to within 2 hours with a written response within 7
days. Details are to be recorded in a complaints register. - Building
condition surveys must be completed before jack hammering etc to all
buildings within 50 metres from the edge. Damage is to be remediated. - Construction
compliance reports must be provided to the director of planning after the
first 6 months of planning detailing compliance. - The
project must be carried out consistent with the Environmental Assessment
COMMUNITY LIAISON
GROUP NOMINEES
A Community Liaison Group has been established to represent
residents concerns in the future. TIDC
has not released names of Goup Members but known community representatives are
listed below – thank you for volunteering!
First meeting is 30 May 2006.
You can contact the
lisison Group via Email at no_stabling_yards@yahoo.com.au
- Belinda
Lucia (Railway Parade) - Gillian
Mauchan (Burren St) - Trevor
Ahearn (Sydney St) - Simon
Lillis (Burren St) - Tim
Hiley (Charles St)
Also thanks to the
following who expressed interest at the meeting in joining the CLG – subject to
TIDC acceptance.
- John
Collins (Charles St), - Peter
Robinson (Henderson Rd) - Nadia
Ballantine-Jones (Pine St)
MORE INFORMATION ON
THE PROJECT
The Review of Environmental Factors, Submissions Report and
Conditions of Approval and other information is available from the TIDC Macdonaldtown
Website at http://www.tidc.nsw.gov.au/ViewSite.aspx?PageID=470
CONTACTS ON
CONSTRUCTION ISSUES
TIDC 24 hour
Construction Response line: 1800 775 465
(Report everything through this line to make sure your
complaint is logged)
Other useful Numbers
TIDC general
project info 1800 684 490
Railcorp
Macdonaldtown Precinct Manager Colin Coakley: 9224 4051 or 0438 606 169
Leighton Community
Relations Manager Alice Pryke: 8198 5102 or 9414 3222
City of Sydney Council –
traffic route compliance/law enforcement unit: 9288 5167 (note regos/time)
Department of
Environment and Conservation: 131 555