July 2018 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 29 June 2018 and it sets out the work expected on the site for the coming months Download: Monthly update Waterloo July 2018.pdf »

April 2018 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 5 April 2018 and it sets out the work expected on the site for the coming months Download: 20180404 Monthly update – Waterloo – April 2018.pdf »

Sydney Metro Presentation on Waterloo Station Construction – 1 Feb 2018

This presentation was made by the construction company John Holland for Sydney Metro about the construction of the tunnels and Waterloo Station box. It was delivered at the REDWatch forum on 1st February 2018 and maps out the timeline for work on the Waterloo Station site. Download: Waterloo Redwatch Presentation.pdf »

January 2018 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 30 January 2018 and it sets out the work expected on the site for the coming months. Download: Monthly update – Waterloo – February 2018._Final docx.pdf »

December 2017 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 5 December 2017 and it sets out the work expected on the site for the coming months. Download: Metro Update Dec 2017.pdf »

Works start at Waterloo Station – Dropin 28 Oct 2017

This leaflet was distributed by Sydney Metro City and Southwest on 24 October 2017 and it sets out the work expected on the site for the coming three months and annouces a Community Connect Session Waterloo Station site office, corner of Wellington Street and Botany Road, Waterloo. When: Saturday 28 October. Time: 9am – 11am … Read more

October 2017 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 5 October 2017 and it sets out the work expected on the site for the coming three months. Download: Monthly update – Waterloo – October 2017 Final.pdf »

September 2017 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 29 September 2017 and it sets out the work expected on the site for the coming three months. Download: 170829_September Monthly Update_ Early Works Waterloo – FINAL_APPROVED.PDF »

August 2017 Metro Waterloo Update

This leaflet was distributed by Sydney Metro City and Southwest on 1 August 2017 and it sets out the work expected on the site for the coming three months. Download: 170725_August Monthly Update_Early Works Waterloo.pdf »

Early Works on Waterloo Station Site from July 2017

This leaflet was distributed by Sydney Metro City and Southwest in late June 2017 and it sets out the work expected on the site from July to September 2017. Download: 170626_July Monthly Update_Early Works Waterloo.pdf »