Report for Social Impact Scoping and Assessment Consultation Outcomes Report May 2012

This is the May 2012 Report from GHD Pty Ltd on the Social Impact Scoping and Assessment Consultation Outcomes undertaken for the Sydney Metropolitian Development Authority (SMDA). This report was released in October 2014 by UrbanGrowth and is to be updated as part of the UrbanGrowth Central to Eveleigh “Social Sustainability Due Diligence Study” currently … Read more

Draft Central to Eveleigh Corridor Concept Plan Precint Map

The draft map of proposed Central to Eveleigh Precincts was provided to focus groups in June 2014. The map shows the proposed precincts in June 2014 and a timeframe for work on those precincts. The location of the precincts covered below is based on the precincts in this map. Page 2 covers six themes UrbanGrowth … Read more

Eveleigh – After Urban Growth Indicative Built Form

This is a screen shot from Chanel 9 news on 7 March 2014 announcing UrbanGrowth NSW was taking responsibility for developments between Central and Parramatta. The presentation showed a fly through of the Eveleigh portion of Central to Eveleigh before and after “Indicative Built Form”. This is the after shot. if you download both photos … Read more

Categories 18, 4

Eveleigh – Before Urban Growth Indicative Built Form

This is a screen shot from Chanel 9 news on 7 March 2014 announcing UrbanGrowth NSW was taking responsibility for developments between Central and Parramatta. The presentation showed a fly through of the Eveleigh portion of Central to Eveleigh before and after “Indicative Built Form”. This is the before shot. if you download both photos … Read more

Categories 18, 4

Redfern Waterloo Heritage Taskforce Final Report 2011

The Redfern Waterloo Heritage Taskforce was established to report by March 2011, the end of the Keneally Gopvernment’s term. This is the final report of the RWHT. The RWHT recomended that there should be an ongoing mechanism for Heritage Co-ordination around the former Eveleigh Railway Workshops. Attempts are still being made to re-establish such a … Read more

Redfern Station Revised Concept Design Report Section D Appendices 2009

This is Part D Appendices of the Redfern Station Revised Concept Design report undertaken by Cox ARUP & Bovis Lend Lease. This part of the report is a scan of the following Appendices: 1 Architecture and Urban design peer review study; 2 Accessibility peer review study; 3 Crowd modelling peer review studies; 4 Engineering peer … Read more

Redfern Station Revised Concept Design Report Section C Cost and Constructability 2009

This is Part C Cost and Constructability of the Redfern Station Revised Concept Design report Section B Engineering Reports undertaken by Bovis Lend Lease. This part of the report is a scan of the Bovis Lend Lease report and deals with Construction Methodology and Program, Station upgrade and development costs and associated Appendices. Financial figures … Read more

Redfern Station Upgrade Concept Design Study Part B – Engineering Reports 2007

This is Part B of the Concept Design Study for the Redfern Station Upgrade of April 2007 undertaken by Connell Wagner. It deals with 1. Preliminary Service Recommendations 2. Requirements for vertical circulation under peak AM loads 3. Pedestrian Evacuation and Fire engineering report 4. STEPS Pedestrian Simulation Modelling results 5. Structural Design Report 6. … Read more

Redfern Station Upgrade – 2007 Proposed OptionsJackson Teece

In 2007 Jackson Teece produced a Concept Design Study for the Redfern Station Upgrade in 2007. They recommended three Options for the redevelopment: a “Base Case” (Option D) that addressed easy access, fire and other compliance issues on basically the same footprint ($29.5m); a “Base Case Plus” (Option E) that included additional works with Lawson … Read more

Redfern Station Upgrade – 2007 Study of preferred options

In 2007 Jackson Teece produced a Concept Design Study for the Redfern Station Upgrade. Appendix 4 of that report reported and assessed a number of previous proposals to upgrade Redfern Station as well as some additional suggestions from Jackson Teece. Jacson Teece’s Option C emerged from this study as the preferred option. It was later … Read more

Redfern Station Upgrade – Gateway Review Planning Session 10 May 2010

This document was the most recent of documents released in October 2013 by Transport NSW to a GIPA request initiated by Lift Redfern regarding planning for the Upgrade of Redfern Railway Station. This documents gives a quick overview of the issues needing to be adressed in upgrading Redfern Station and the key options considered. This … Read more

Lord Mayor Letter of Congratulation to Lift Redfern

This is the letter requested in the Council Meeting resolution on 26th August 2013 concerning Lift Redfern. In the leter the Lord Mayor says “I write to congratulate Lift Redfern on last week’s announcement that the NSW Government will provide some lift access at Redfern Station. This is an important first step in making Redfern … Read more

RWA Land Use Zoning Map

This map shows the Land Use Zoning for the RWA area. File is 344 kB PDF Download: SEPP_MD_RWA_LZN_001_20110913.pdf »

RWA Land Application Map (325 kB)

This map shows the land covered by the RWA’s planning controls. File is 325 kB Download: SEPP_MD_RWA_LAP_001_20110913.pdf »

RWA Height of Buildings Map

This is the RWA Height of Buildings Map. File is 346 kB. Download: SEPP_MD_RWA_HOB_001_20110913.pdf »

Heritage Map

This is the RWA Heritage Map covering Redfern amd Eveleigh Heritage. File is 338 kB. Download: SEPP_MD_RWA_HER_001_20110913.pdf »